Traceability
The ability to relate items in test documentation to each other and to the test basis, e.g. linking test cases to requirements.
Syllabus chapters: 1
Sources: ISTQB® Certified Tester Foundation Level syllabus 4.0.1 and the official ISTQB® Glossary. Glossary content © International Software Testing Qualifications Board; source: glossary.istqb.org.
Related terms
Traceability in a practice question
Question 1
A test manager needs to state to what extent the test objectives have been achieved. What makes that possible, and what has to be in place for it?
- The test completion report, provided that every planned test case has been executed
- Accurate traceability, provided that measurable coverage criteria are defined in the test basis
- The defect report backlog, provided that every reported defect has been triaged
- The test execution schedule, provided that it was followed without any deviation
Show answer
- The test completion report, provided that every planned test case has been executedThe completion report presents the evaluation; it is not what makes the evaluation possible.
- Correct answer: Accurate traceability, provided that measurable coverage criteria are defined in the test basisTraceability, together with measurable coverage criteria in the test basis.
- The defect report backlog, provided that every reported defect has been triagedTriaging defects says nothing about how far the test objectives were met.
- The test execution schedule, provided that it was followed without any deviationFollowing the schedule shows tests ran, not what coverage they achieved.
Accurate traceability supports coverage evaluation, so it is very useful if measurable coverage criteria are defined in the test basis. Those coverage criteria can then function as key performance indicators that drive the activities showing to what extent the test objectives have been achieved. Traceability without measurable criteria in the test basis cannot carry that judgement.
Syllabus section 1.4.4
Question 2
A team analyzes its test basis, identifies testable features, defines and prioritizes test conditions, and establishes bidirectional traceability to the test basis. Why are these tasks part of test analysis?
- They determine what to test in terms of measurable coverage criteria
- They create test suites and derive test cases from test conditions
- They run test procedures and compare actual with expected results
- They compare actual progress against the test plan and trigger control actions
Show answer
- Correct answer: They determine what to test in terms of measurable coverage criteriaThese tasks determine what to test as measurable coverage criteria.
- They create test suites and derive test cases from test conditionsCreating test suites and deriving test cases are test design tasks that determine how to test.
- They run test procedures and compare actual with expected resultsRunning procedures and comparing results are test execution tasks.
- They compare actual progress against the test plan and trigger control actionsComparing progress with the plan and taking action belong to test monitoring and control.
Test analysis determines what to test in terms of measurable coverage criteria. Its major tasks include analyzing the test basis, identifying testable features, defining and prioritizing test conditions, and establishing bidirectional traceability between the test basis and test conditions.
Syllabus section 1.4.1
Original PrepBench practice material, not official exam questions or exam dumps. PrepBench is independent and is not affiliated with or endorsed by ISTQB®.