Test plan

Documentation describing the objectives, scope, approach, resources, and schedule of intended test activities.

Syllabus chapters: 5

Sources: ISTQB® Certified Tester Foundation Level syllabus 4.0.1 and the official ISTQB® Glossary. Glossary content © International Software Testing Qualifications Board; source: glossary.istqb.org.

Related terms

Test plan in a practice question

Question 1

A test manager is asked why the team is spending time writing a test plan when the schedule is already tight. Which answer reflects what test planning does?

  1. It records what was tested and what the results were, so the team can show afterwards that testing took place
  2. It makes the testers confront the future challenges of the project — risks, schedule, people, tools, costs and effort
  3. It settles the test approach in advance, so that it does not have to be reconsidered once test execution starts
  4. It moves responsibility for the quality of the release to the stakeholders who approve the plan
Show answer
  • It records what was tested and what the results were, so the team can show afterwards that testing took placeRecording what was tested and the results is the work of test logs and reports.
  • Correct answer: It makes the testers confront the future challenges of the project — risks, schedule, people, tools, costs and effortPlanning forces the testers to confront risks, schedule, people, tools, cost and effort.
  • It settles the test approach in advance, so that it does not have to be reconsidered once test execution startsA test plan may be revised; test control exists precisely to adjust as circumstances change.
  • It moves responsibility for the quality of the release to the stakeholders who approve the planA test plan is a means of communication with stakeholders; it does not transfer responsibility.

Test planning guides the testers' thinking and forces them to confront the future challenges related to risks, schedules, people, tools, costs and effort. Preparing a test plan is a useful way to think through the efforts needed to achieve the test objectives; the value is in the thinking it forces, not only in the document it produces.

Syllabus section 5.1.1

Question 2

What distinguishes a test progress report from a test completion report?

  1. Progress reports are produced by the test team; completion reports by the stakeholders
  2. Progress reports support ongoing test control; completion reports summarize a finished test activity
  3. Progress reports record defects; completion reports record the metrics that were collected
  4. Progress reports follow a set template; completion reports are informal and ad hoc
Show answer
  • Progress reports are produced by the test team; completion reports by the stakeholdersThe test team generates progress reports for stakeholders to keep them informed.
  • Correct answer: Progress reports support ongoing test control; completion reports summarize a finished test activityOngoing control against summarizing a completed test activity.
  • Progress reports record defects; completion reports record the metrics that were collectedBoth report types include metrics; neither is limited to recording defects.
  • Progress reports follow a set template; completion reports are informal and ad hocThis is the wrong way round: completion reporting follows a set template.

Test progress reports support the ongoing test control and must provide enough information to modify the test schedule, resources or test plan when circumstances change. A test completion report is prepared during test completion, when a project, test level or test type is complete and its exit criteria have ideally been met, and summarizes that activity. Test progress reporting within a team is often frequent and informal, while completion reporting follows a set template and occurs only once.

Syllabus section 5.3.2