Project risk
A risk that threatens the project's ability to deliver, e.g. schedule slips, skill shortages, or supplier issues.
Syllabus chapters: 5
Sources: ISTQB® Certified Tester Foundation Level syllabus 4.0.1 and the official ISTQB® Glossary. Glossary content © International Software Testing Qualifications Board; source: glossary.istqb.org.
Related terms
Project risk in a practice question
Question 1
Which of the following is a PRODUCT risk rather than a project risk?
- A key tester leaves the company during the release
- The third-party test environment provider delivers late
- The application calculates incorrect insurance premiums
- The development team is cut by 20% in the middle of the project
Show answer
- A key tester leaves the company during the releaseA tester leaving threatens delivery — that is a project risk, not a product risk.
- The third-party test environment provider delivers lateA late supplier is a project risk affecting the ability to deliver.
- Correct answer: The application calculates incorrect insurance premiumsIncorrect premium calculations are a defect in the product's quality — a product risk.
- The development team is cut by 20% in the middle of the projectA staffing cut endangers the project's delivery — a project risk.
Product risks relate to the quality of the product itself — e.g. incorrect calculations, poor performance, security weaknesses. Staff departures, supplier delays, and budget cuts threaten the project's ability to deliver and are project risks.
Syllabus section 5.2.2
Question 2
Which of the following is a PROJECT risk rather than a product risk?
- The only tester with payments domain knowledge may leave before the release
- The app crashes whenever the network connection drops
- The search results returned are sometimes incorrect
- Response times exceed the agreed limit under heavy load
Show answer
- Correct answer: The only tester with payments domain knowledge may leave before the releaseLosing the only skilled tester threatens delivery — a project risk.
- The app crashes whenever the network connection dropsA crash on network loss is a defect in the product — a product risk.
- The search results returned are sometimes incorrectIncorrect search results are a product-quality problem — a product risk.
- Response times exceed the agreed limit under heavy loadExceeding response-time limits is a performance defect of the product — a product risk.
Project risks threaten the project's ability to deliver — organizational issues like skill shortages and staff departures, supplier problems, technical/schedule issues. Crashes, wrong results, and slow responses are quality problems of the product itself: product risks.
Syllabus section 5.2.2