A risk that threatens the project's ability to deliver, e.g. schedule slips, skill shortages, or supplier issues.

Syllabus chapters: 5

Sources: ISTQB® Certified Tester Foundation Level syllabus 4.0.1 and the official ISTQB® Glossary. Glossary content © International Software Testing Qualifications Board; source: glossary.istqb.org.

Related terms

Project risk in a practice question

Question 1

Which of the following is a PRODUCT risk rather than a project risk?

  1. A key tester leaves the company during the release
  2. The third-party test environment provider delivers late
  3. The application calculates incorrect insurance premiums
  4. The development team is cut by 20% in the middle of the project
Show answer
  • A key tester leaves the company during the releaseA tester leaving threatens delivery — that is a project risk, not a product risk.
  • The third-party test environment provider delivers lateA late supplier is a project risk affecting the ability to deliver.
  • Correct answer: The application calculates incorrect insurance premiumsIncorrect premium calculations are a defect in the product's quality — a product risk.
  • The development team is cut by 20% in the middle of the projectA staffing cut endangers the project's delivery — a project risk.

Product risks relate to the quality of the product itself — e.g. incorrect calculations, poor performance, security weaknesses. Staff departures, supplier delays, and budget cuts threaten the project's ability to deliver and are project risks.

Syllabus section 5.2.2

Question 2

Which of the following is a PROJECT risk rather than a product risk?

  1. The only tester with payments domain knowledge may leave before the release
  2. The app crashes whenever the network connection drops
  3. The search results returned are sometimes incorrect
  4. Response times exceed the agreed limit under heavy load
Show answer
  • Correct answer: The only tester with payments domain knowledge may leave before the releaseLosing the only skilled tester threatens delivery — a project risk.
  • The app crashes whenever the network connection dropsA crash on network loss is a defect in the product — a product risk.
  • The search results returned are sometimes incorrectIncorrect search results are a product-quality problem — a product risk.
  • Response times exceed the agreed limit under heavy loadExceeding response-time limits is a performance defect of the product — a product risk.

Project risks threaten the project's ability to deliver — organizational issues like skill shortages and staff departures, supplier problems, technical/schedule issues. Crashes, wrong results, and slow responses are quality problems of the product itself: product risks.

Syllabus section 5.2.2