Impact analysis
Identifying the areas affected by a change, including intended consequences and side effects, to scope maintenance and regression testing.
Syllabus chapters: 2
Sources: ISTQB® Certified Tester Foundation Level syllabus 4.0.1 and the official ISTQB® Glossary. Glossary content © International Software Testing Qualifications Board; source: glossary.istqb.org.
Related terms
Impact analysis in a practice question
Question 1
An insurer will take its legacy policy application out of service at the end of the year, but regulation requires the policy data to stay retrievable for ten more years. Which maintenance trigger is this, and what testing does it call for?
- A modification, calling for tests of the planned enhancement and regression tests of the rest
- Retirement, calling for tests of data archiving and of the restore and retrieval procedures
- An upgrade or migration, calling for tests of data conversion into the system being maintained
- A hot fix, calling for confirmation of the corrective change and an impact analysis of the areas hit
Show answer
- A modification, calling for tests of the planned enhancement and regression tests of the restModifications are planned enhancements, corrective changes or hot fixes; nothing is being changed here.
- Correct answer: Retirement, calling for tests of data archiving and of the restore and retrieval proceduresAn application reaching the end of its life is retirement, and long retention makes archiving and retrieval testing necessary.
- An upgrade or migration, calling for tests of data conversion into the system being maintainedUpgrades or migrations move the operational environment or migrate data into the maintained system.
- A hot fix, calling for confirmation of the corrective change and an impact analysis of the areas hitA hot fix is an unplanned corrective release; no defect is being corrected in this situation.
The triggers for maintenance and maintenance testing are classified as modifications, upgrades or migrations of the operational environment, and retirement. Retirement occurs when an application reaches the end of its life; it can require testing of data archiving if long data retention periods are required, and testing of restore and retrieval procedures after archiving may also be needed in case certain data is required during the archiving period.
Syllabus section 2.3.1
Question 2
Before deciding whether to make a change to an operational system, a team works out the potential consequences the change would have in other areas of the system. What is this called?
- Root cause analysis
- Risk analysis
- Impact analysis
- Test analysis
Show answer
- Root cause analysisRoot cause analysis establishes why a defect arose, not what a proposed change would affect.
- Risk analysisRisk analysis assesses risk; it does not map the consequences of a specific change.
- Correct answer: Impact analysisImpact analysis assesses the potential consequences in other areas of the system.
- Test analysisTest analysis identifies test conditions from the test basis; it does not evaluate a change.
Impact analysis may be done before a change is made, to help decide if the change should be made, based on the potential consequences in other areas of the system. It is also advisable before regression testing, where it shows which parts of the software could be affected and so indicates the extent of the regression testing needed.
Syllabus section 2.3
Original PrepBench practice material, not official exam questions or exam dumps. PrepBench is independent and is not affiliated with or endorsed by ISTQB®.